4. Determine Required Project Results
PMP Practice Exam System
Professional PMP Practice Exams with instant access from any browser --
nothing to download. More than one thousand realistic PMP exam questions. Detailed explanations and
PMBOK references for every question. |
What you need to accomplish or deliver in order to make good on the project's goals
and objectives will make up the required project results.  ou're ready to list the requirements of your project when you
have completed the project definition with fully-described goal, objectives, boundaries and constraints
-- and after you have obtained complete buy-in from sponsor, customers, and other stakeholders.
Translate the project scope definition into
requirements. Start with the list of objectives and, for each
one, create a list of project results that satisfy that objective. This is simply a list, as
detailed as possible, that describe conditions or deliverables that are needed to meet the objectives. The
items should represent actions of one kind or another. A required project result
should be stated as a condition that has already been met -- for example, all employees
trained, documentation delivered, fully-assembled widget or framing
completed.
Organize the requirements into logical groups or phases. These
groups will be used in defining the workload. Each group or phase will become a work
package that will be further broken down into tasks for fulfilling the requirements or producing the
deliverables for that work package. For example, in a new home project you might have the following
requirements:
- Site prepared
- Foundation completed
- Framing completed
- Roofing completed
- Windows and doors installed
- Electrical roughed in
- Plumbing roughed in
- Heating & cooling ductwork installed
- etc. - For a complete list
try: How Stuff Works
The site preparation work package could be broken down further into: 1) Trees
and boulders cleared, 2) basement excavation completed, 3) final grading
completed.
The plumbing work package might include 1) kitchen rough-in complete, 2) first floor
half-bath complete, 3) exterior taps
installed etc.
These groups are not the same thing and not as
detailed as tasks. A task grouping could be "doors and windows installed". The tasks associated with
the grouping will include individual tasks for each door or window and will be defined in the next
step.
Get stakeholder agreement on the required project results.
This is a critical planning step that should be done carefully and deliberately. Failure to get consensus
could mean there are errors in the plan and errors that occur here will be compounded as the project moves
forward and will be difficult to correct once things have been underway for awhile.
When you've finished listing requirements for the project you're ready to
create the work breakdown structure and work packages , and start building your task
list.
Next in the series:
Defining the Workload
- Jake Alexander

|