12. Report Project Status
The best ways to report project status on the projects include comparing actual cost
and schedule against the planned cost and schedule, indicating corrective actions taken and forecasting
adjustments if needed.  n the same way that you expect your team
members to be accurate and timely in reporting task status to you, you must report project status in a
timely way to your sponsor, customers, and stake holders. In doing so, you have an
opportunity to take credit for the things you and your team have done well and get direction on situations
where help is needed.
Communicate accurately and often.
Your sponsor, customer and stakeholder will take bad news more easily if it's presented to them in time to provide
direction or make suggestions to correct them. If you report project status in time to take action, you make your
stakeholders partners in decision-making for the project, even if the decision is to pull the plug. The
worse thing you could do would be to wait until most of the budget has been spent before letting them know that the
project is hopelessly behind schedule and consuming funds twice as fast as expected. Give them the opportunity to
help and offer suggestions.
Focus on schedule, cost, achievement, and changes.
When you report project status to the decision-makers you'll want to emphasize progress against the
schedule for the entire project, and for tasks with exceptional variances. You'll want to report on
expenditures for the whole project, and for tasks with exceptional cost variances. Run down the list of
deliverables, indicating those that were delivered on time, delivered late, or behind schedule. Finally, identify
any changes that have been made to the project like additional tasks and deliverables, or resources pulled for use
elsewhere. Indicate where the changes affected the project. The best way to accomplish the reporting is to use
baseline and actual comparisons.
Highlight budget revisions by comparing current budget to the original
baseline. Show changes that have been made to the project, by
comparing your revised budget or baseline to the original baseline you saved when the scope was approved. Compare
Costs and tasks against the schedule timeline and identify any tasks that were changed due to requirements or
resource changes. This comparison should only be showing changes that have been
approved.
Report project status by comparing actuals to the current
budget. By comparing actual progress to the most recent budget revision you show how things stand
that have occurred since the revisions were approved and since the last reporting session. Here's where you will
want to talk about tasks that are going according to plan, as well as those that are falling behind
or concuming budget too quickly.
Use variances to forecast future performance. You'll want to give
them an idea of the project outcomes based on events and progress so far, and on projections of current trends in
cost and schedule variances. Where possible, indicate schedule trends like tasks appear to be
averaging 20% longer than anticipated. Obviously, only one delayed task out of 50 wouldn't indicate a trend.
You can show trends in costs either on a task by task basis or as an overall project spending rate, also known as
the burn rate. For example, we're spending about $150 more per week than planned.
Present an action plan to correct or improve progress. You should
never make the sponsor, customer and stakeholders come up with a plan. They will resent having to do it and
you will rarely be satisfied with what they suggest. Instead, develop your own plan and present it to them. Then
give them the opportunity to accept it, change it, or suggest alternatives.
Sometimes negotiation is your only
option. When you have problems that are uncorrectable, often your only choice is to adjust the
project's cost, schedule, or requirements to compensate or accommodate the changes. When you need to do that,
you'll need the approval of the sponsor, the customer, and perhaps the stakeholders. To get that approval you may
need to negotiate the changes. Be prepared to communicate progress and talk about solutions. In some cases it
may be advisable to have two or three possible solutions or scenarios up your sleeve.
Remember to report project status often and whenever
significant events occur. It's easier to make course corrections if you do it right away. Wait too long, and you
could be too far off course to recover.
- Jake
Alexander
Next in the series: Closing the
Project
|